|
|
|
|
|
Contents
2.1.1 Monitoring Requirements and
Equipment
2.1.2 Monitoring Schedule for the
Reporting Month
2.1.3 Results and Observations
2.2.1 Monitoring Requirements and
Equipment
2.2.2 Monitoring Schedule for the
Reporting Month
2.2.3 Results and Observations
2.5.1 Preserved Plant Species of
Conservation Importance
2.5.2 Transplanted Plant Species of
Conservation Importance
2.7
Soft Shore
Ecological Monitoring
2.10 LANDSCAPE AND VISUAL
MONITORING
2.11 IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURES
2.12 SUMMARY OF COMPLAINTS, NOTIFICATION OF SUMMONS AND SUCCESSFUL
PROSECUTIONS
ANNEX b
Environmental Mitigation Implementation Schedule
ANNEX c
Status of Submissions and Implementation Status of Mitigation Measures
under EP
ANNEX d
Status of Statutory Environmental Requiremens
ANNEX e1
Calibration Certificates for Air Quality
ANNEX e2
Monitoring Schedule for Air Quality
ANNEX e3
Monitoring Results for Air Quality
ANNEX e4
Event and Action Plan for Air Quality
ANNEX f1
Calibration Certificates for Noise
ANNEX f2
Monitoring Schedule for Noise
ANNEX f3
Monitoring Results for Noise
ANNEX f4
Event and Action Plan for Noise
ANNEX g
Compensation Woodland Monitoring
ANNEX h
Preserved/Transplanted Plant Species of Conservation Importance
Monitoring
ANNEX h1 Preserved
Plant Species of Conservation Importance
ANNEX h2 Transplanted
Plant Species of Conservation Importance
ANNEX i
Eco-shoreline Monitoring
annex j3 event and action plan
ANNEX K Landscape
and Visual Monitoring
ANNEX K1 Examples of
Landscape and Visual Mitigation Measures
ANNEX K2 Event and
Action Plan for Landscape and Visual Mitigation Measures
ANNEX M
Monitoring Schedule for the Next Reporting Period
List of Tables
Table 1.1 Contact Information of Key
Personnel
Table 1.2 Major Activities in the Reporting
Period
Table 1.3 Summary of Status for the
Environmental Aspects under the Updated EM&A Manual
Table 2.1 Action and Limit Levels for 1-hour
TSP
Table 2.2 Air Quality Monitoring Details
Table 2.3 Summary of 1-hour TSP Monitoring
Results in the Reporting Period
Table 2.4 Action and Limit Levels for
Construction Noise
Table 2.5 Noise Monitoring Details
Table 2.6 Summary of Construction Noise
Monitoring Results in the Reporting Period
Table 2.7 Summary of Qualitative Walk-through
Surveys
Table 2.8 Results of Sedimentation Rate
Monitoring
Table 2.9 Key Observations Identified during
the Site Inspection in this Reporting Month
Table 2.10 Quantities of Different Waste Generated and
Imported Fill Materials
Table 2.11 Implementation Status of Landscape and
Visual Mitigation Measures
LIST OF FIGURES |
|
LOCATION OF CONTRACT NO. NL/2017/03 – TUNG CHUNG NEW TOWN EXTENSION – RECLAMATION AND ADVANCE WORKS (CONTRACT 1) |
|
LOCATION OF CONTRACT NO. NL/2020/02 – TUNG CHUNG NEW TOWN EXTENSION – SALT WATER SUPPLY SYSTEM (CONTRACT 2) |
|
LOCATION OF CONTRACT NO. NL/2020/03 – TUNG CHUNG NEW TOWN EXTENSION – MAJOR INFRASTRUCTURE WORKS IN TUNG CHUNG EAST (CONTRACT 3) |
|
LOCATION OF CONTRACT NO. NL/2020/02 – TUNG CHUNG NEW TOWN EXTENSION – TAI HO INTERCHANGE (CONTRACT 7) |
|
CONSTRUCTION DUST MONITORING STATION LOCATION |
|
CONSTRUCTION AIRBORNE NOISE MONITORING STATION LOCATION |
|
MARINE ECOLOGICAL MONITORING (INTERTIDAL SOFT-SHORE HABITATS) |
|
REPRESENTATIVE PHOTOGRAPHS TAKEN DURING THE IMPACT SOFT SHORE ECOLOGICAL MONITORING CONDUCTED IN MARCH 2024 |
Acronyms
and abreviations
Acronyms |
Description |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CEDD |
Civil Engineering and Development Department |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
EIS |
Ecologically Important Stream |
EM&A |
Environmental Monitoring and Audit |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
ER |
Engineer's Representative |
ERM |
ERM-Hong Kong, Limited |
ET |
Environmental Team |
HVS |
High Volume Sampler |
IEC |
Independent Environmental Checker |
PDA |
Planned Development Area |
PME |
Powered Mechanical Equipment |
QPME |
Quality Powered Mechanical Equipment |
RAP |
Remediation Action Plan |
RR |
Remediation Report |
RTTM |
Real Time Tracking and Monitoring |
SS |
Suspended Solid |
TCB |
Tung Chung Bay |
TCE |
Tung Chung East |
TCNTE |
Tung Chung New Town Extension |
TCW |
Tung Chung West |
The Project |
Tung Chung New Town Extension (East) |
THW |
Tai Ho Wan |
TSP |
Total Suspended Particulate |
Updated EM&A Manual |
Updated Environmental Monitoring and Audit Manual for Tung Chung New Town Extension prepared by ERM under Agreement No. CE 60/2017 (EP) and deposited to EPD under Environmental Permit No. EP-519/2016 |
Tung Chung New Town Extension (TCNTE) is one of the major
initiatives under the Government's multi-pronged approach to increase land
supply to meet Hong Kong's medium- to long-term needs for housing, economic and
social developments. The Environmental Impact Assessment (EIA) Report for
TCNTE (Register No. AEIAR-196/2016) was approved on 8 April 2016 and the
Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP
cover both Tung Chung East (TCE) and Tung Chung West (TCW). ERM-Hong
Kong, Limited (ERM) is commissioned to undertake the role of Environmental Team
(ET) for the construction and operation of TCE Project (“the Project”) in
accordance with the requirements specified in the EP, Updated Environmental
Monitoring and Audit (EM&A) Manual, EIA Report of the TCNTE project and
other relevant statutory requirements.
The construction of the Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance
Works (“Contract 1”) at TCE commenced on 9 July 2018.
The construction of the Contract No. NL/2020/02 - Tung Chung
New Town Extension – Salt Water Supply System
(“Contract 2”) at TCE commenced on 4 September 2021.
The construction of the Contract No. NL/2020/03 - Tung Chung
New Town Extension – Major Infrastructure Works in Tung Chung East (“Contract
3”) at TCE commenced on 5 November 2021.
The construction of the Contract No. NL/2020/07 - Tung Chung
New Town Extension – Tai Ho Interchange (“Contract 7”) at TCE commenced on 15
March 2022.
This is the Monthly EM&A report presenting the EM&A
works carried out during the period from 1 to 31 March 2024 for the TCE Project
in accordance with the Updated EM&A Manual.
A summary of monitoring and audit activities conducted in
the reporting period is listed below:
Air Quality
Monitoring
6 sessions
Noise
Monitoring
6 sessions
Compensation Woodland
Monitoring 1 session
Preserved Plant
Species Monitoring
1 session
Transplanted
Plant Species Monitoring 1 session
Soft Shore
Ecological
Monitoring
1 session
Environmental Site Inspection
·
Contract
1
4 sessions
·
Contract
2
4 sessions
·
Contract
3
5 sessions
·
Contract
7
4 sessions
Environmental Management Meeting
·
Contract
1
1 session
·
Contract
2
1 session
·
Contract
3
1 session
·
Contract
7
1 session
Environmental auditing works, including weekly site
inspections of construction works conducted by the ET, audit of implementation
of Complaint Management Plan, Eco-shoreline Implementation Plan, Detailed
Preservation and/or Translocation of Plant Species of Conservation Importance,
Detailed Compensatory Woodland Planting Plan and Waste Management Plan were conducted in the
reporting period. Based on the audit results and the observation for the
reporting period, environmental pollution control and mitigation measures for
the Project were properly implemented.
No exceedance of Action and Limit Levels was recorded for
construction air quality monitoring in the reporting period.
No exceedance of Limit Levels was recorded for
construction noise monitoring in the reporting period. However, one (1) Action Level was triggered from one (1)
environmental complaint related to noise nuisance in the reporting period.
Water quality monitoring was suspended in the reporting
period.
The construction of vertical eco-shoreline, mangrove
eco-shoreline and rocky eco-shoreline has been substantially completed. No monitoring was conducted during the reporting period.
Based on the post-construction monitoring conducted during
the reporting period, there was no evidence showing any significant difference
in intertidal communities when compared against the data obtained during
baseline monitoring. The ET will continue to observe the change in
density or the distribution pattern of horseshoe crab, seagrass and intertidal
soft shore communities taking into account natural
fluctuation in respect of the occurrence and distribution pattern.
There was no notification of summons or prosecution
recorded in the reporting period.
Two (2) environmental complaints related to Contract 3 was
received in the reporting period. Investigations were conducted for the
environmental complaints in accordance with the complaint handling process as
stated in the Complaint Management Plan.
There was no reporting change in
the reporting period.
Potential environmental impacts arising from the upcoming
construction activities in the next reporting period of April 2024 are mainly
associated with dust emission, noise from plant operation during normal working
hours and restricted hours, handling and storage of C&D materials generated
from construction activities, efficiency of wastewater and drainage management
and tree protection. The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures. The ET will also recommend to the
Contractor about the environmental toolbox topics on the abovementioned key
issues for the coming month.
Tung Chung New Town Extension (TCNTE) is one of the major
initiatives under the Government's multi-pronged approach to increase land
supply to meet Hong Kong's medium- to long-term needs for housing, economic and
social developments. The Environmental Impact Assessment (EIA) Report for TCNTE
(Register No. AEIAR-196/2016) was approved on 8 April 2016 and the
Environmental Permit (EP) No. EP-519/2016, covering the construction and
operation of TCNTE, was granted on 9 August 2016. The EIA Report and EP cover both
Tung Chung East (TCE) and Tung Chung West (TCW).
ERM-Hong Kong, Limited (ERM) is commissioned to undertake
the role of Environmental Team (ET) for the construction and operation of TCE
Project (“the Project”) in accordance with the requirements specified in the
EP, Updated Environmental Monitoring and Audit (EM&A) Manual ([1]), EIA Report of the TCNTE project ([2]) and other relevant statutory
requirements.
The TCNTE comprises the
following elements:
(a) TCE Project
1. Reclamation of the seabed by a non-dredged method at
TCE to form a total of about 130 hectares of land;
2. Construction of about 4.9 kilometers
of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three
circulation drains and a seawater intake at TCE;
3. Provision of infrastructure for Tung Chung Area 58,
including construction of a single two-lane road with a footpath and the
associated utility works;
4. Construction of proposed open space;
5. Construction of roads, footpaths, cycle tracks and the
associated junction / road improvement works;
6. Engineering infrastructure works covering drainage,
sewerage, waterworks (including a fresh water service
reservoir, a salt water service reservoir and a salt water pumping station),
common utility tunnels and landscaping works; and
7. Implementation of environmental mitigation measures
and environmental monitoring and audit programme for the works.
(b) TCW Project
1. Site formation works at TCW;
2. Construction of proposed open space;
3. Construction of the River Park
including a visitor centre at TCW; and
4. Construction of sustainable urban drainage systems at TCW.
The locations of Contracts 1, 2, 3 and 7 are shown in Figure 1.1 to 1.4. The construction and the
reclamation related marine works of Contract 1 commenced on 9 and 13 July 2018,
respectively. The construction of Contracts 2, 3 and 7 commenced on 4
September 2021, 5 November 2021 and 15 March 2022, respectively.
This is the Monthly EM&A Report for the TCE Project
which summarises the key findings of the EM&A programme during the reporting period from 1 to 31 March
2024 for the construction works.
The organization structure of
the Project is shown in Annex
A. The key personnel contact names and contact details are
summarized in Table 1.1 below.
Table 1.1
Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Environmental Team (ET) (ERM-Hong Kong, Limited) |
ET Leader |
Kelvin So |
3894 9504 |
Deputy ET Leader |
Raymond Chow |
3894 9509 |
|
Independent Environmental Checker (IEC) (Binnies Hong Kong Limited) |
IEC |
Manuel Chua |
3894 9807 |
Deputy IEC |
Edward Lau |
3894 9695 |
|
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
|||
Civil Engineering and Development Department |
Senior Geotechnical Engineer |
C H Yan |
3894 9702 |
Marine Conservation Officer |
Wo King Tai |
3894 9707 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Chris Cheung |
3894 9604 |
|
Senior Resident Engineer |
Chris Chow |
3894 9651 |
|
Resident Engineer |
Victor Chan |
3894 9666 |
|
Senior Inspector of Works |
C K Liu |
3894 9733 |
|
Contractor (Build King – SCT Joint Venture)
|
Site Agent |
David Wong |
9653 8635 |
Civil Division Head |
Marco Chan |
9257 7033 |
|
Environmental Officer |
Issac Wong |
9873 8968 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Patrick C Y Yeung |
2231 4435 |
Electrical & Mechanical Engineer |
Samson K L Yip |
2231 4460 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Sunny Ng |
3894 9605 |
|
Senior Resident Engineer |
Vincent Leung |
3894 9645 |
|
Resident Engineer |
Amen Fung |
3894 9676 |
|
Senior Inspector of Works |
Wong Ting Yu |
3894 9706 |
|
Contractor (China Geo-Engineering Corporation)
|
Construction Manager |
Ambrose Kwong |
6198 7787 |
Site Agent |
Aaren Li |
6468 8138 |
|
Construction Team Leader |
Aaren Li |
6468 8138 |
|
Environmental Officer |
Peter Ho |
9457 0120 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
|||
Civil Engineering and Development Department
|
Senior Engineer |
Eddie W C Lam |
2231 4445 |
Senior Engineer |
Phoebe Tang |
2231 4423 |
|
Engineer |
Timothy H M Chan |
2231 4473 |
|
Engineer |
Colin K C Wong |
2231 4417 |
|
Engineer |
Wing Chen |
3894 9704 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited)
|
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Chief Resident Engineer |
Gloria Tang |
3894 9639 |
|
Senior Resident Engineer |
Winston Wong |
3894 9650 |
|
Resident Engineer |
David Li |
3894 9684 |
|
Resident Engineer |
Alvis Li |
3894 9558 |
|
Resident Engineer |
Anson Yip |
3894 9559 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9737 |
|
Contractor (Build King Civil Engineering Limited)
|
Construction Manager |
Cheung Siu Lun |
2272 3680 |
Site Agent |
Paul Lui |
9095 7922 |
|
Deputy Site Agent |
Aldous Lo |
9225 0368 |
|
Construction Team Leader |
Ken Yau |
9197 2219 |
|
Environmental Officer |
Tim Lin |
6390 0018 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
|
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
|||
Civil Engineering and Development Department |
Senior Engineer |
Phoebe Tang |
2231 4423 |
Engineer |
S H Leung |
2231 4449 |
|
Engineer’s Representative (ER) (AECOM Asia Company Limited) |
Principal Resident Engineer |
Frankie Fan |
3894 9603 |
Senior Resident Engineer |
Kelvin Kwan |
3894 9641 |
|
Senior Resident Engineer |
Brian Li |
3894 9556 |
|
Resident Engineer |
Kingsley Ho |
3894 9552 |
|
Resident Engineer |
Carl Yu |
3894 9671 |
|
Senior Inspector of Works |
Douglas Ng |
3894 9554 |
|
Contractor (Build King Civil Engineering Limited) |
Site Agent |
Hon Yee |
9090 3109 |
Deputy Site Agent |
Vincent Kwan |
9833 1313 |
|
Construction Team Leader |
Vincent Lo |
9883 9229 |
|
Environmental Officer |
Nash Wong |
9810 1946 |
|
24-hour Complaint Hotline |
- |
5976 1853 |
As informed by the Contractor,
details of the major works carried out in this reporting period are listed
below:
Table 1.2
Major Activities in the Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Box culvert construction |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· E&M and ABWF for pumping station at Portion 6 · Construction of service reservoir at Portion 3 · CLP cable duct laying works at Wong Lung Hang at Portion 3 · Watermain laying works at Portion 3 along Chung Yan Road, Man Tung Road, Yu Tung Road Planter and inside WSD facilities · Grouting works at jacking pit at Portion 3 · Watermain laying works at Yi Tung Road at Portion 4 · Manhole construction and pipe laying for drainage works at Portion 5A |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation and pipe laying for rising main and watermain at Portion 146-1 to 146-14 · RC for Pak Mong bridge pile cap at Portion 146-3 · Trench excavation, pipe piles and pipe laying works at Portions 32 (Sham Shui Kok Drive), Portion 34 Phase 2, and Portion 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot), pipe piles at West Gate · Pipe laying and backfilling at Portion 33 · Establishment of pipe jacking works at Portion 33 · ELS and grout curtain at Portion 32 for Receiving pit · RC construction of retaining walls FR1 · RC works for Pak Mong Subway Extension Phase 1 · ELS at Casting Yard A1 and A2 · Bored piles at A1a and A2b · ELS at A2a and RW-R6 · RC works for RW-R2, RW-R3 and ELS for RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 · Mini-piles at Wall E · GI works for open space at Portions 147-1 &2 · Bored piles at Bridge C Portion 146-12 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The environmental mitigation implementation schedule is
presented in Annex B.
The status for all environmental
aspects is presented in Table 1.3. The EM&A requirements
remained unchanged during the reporting period.
Table 1.3
Summary of Status for the Environmental Aspects under the Updated
EM&A Manual
Parameters |
Status |
|
Air Quality |
||
Baseline Monitoring |
The results of baseline air quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted three times every six days |
|
Noise |
|
|
Baseline Monitoring |
The results of baseline noise monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going for TCE, monitoring conducted once per week |
|
Impact Monitoring for Road Traffic Noise during Operational Phase |
To be conducted during operational phase |
|
Fixed Noise Commissioning Test |
To be implemented by the Contractor before operation of TCNTE |
|
Water Quality |
|
|
Baseline Monitoring |
The results of baseline water quality monitoring for TCE were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
Suspended for TCE with approval from EPD |
|
Waste Management |
|
|
Waste Monitoring |
On-going |
|
Land Contamination |
|
|
Contamination Assessment Plan (CAP), Remediation Action Plan (RAP) and Remediation Report (RR) |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Ecology |
|
|
Monitoring for Compensation Woodland
|
Compensation Woodland Planting was completed on 30 September 2022 On-going, monitoring conducted quarterly |
|
Monitoring for Emergent Plant inside the future River Park |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Translocated Amphibians of Conservation Importance |
To be conducted under TCW. Refer to the EM&A Reports of TCW. |
|
Monitoring for Preserved/Transplanted Plant Species of Conservation Importance
|
On-going, for preserved plant species, monitoring conducted once per month; for transplanted plant species, replacement planting was carried out on 28 April 2023 and 19 September 2023, and monitoring conducted once per month for the first year |
|
Monitoring for Tung Chung Stream EIS and Wong Lung Hang EIS
|
To be conducted under TCW. Refer to the EM&A Reports of TCW. Monitoring for Wong Lung Hang was not required and the proposal was accepted by EPD on 2 September 2021 |
|
Eco-shoreline Monitoring |
The dry season monitoring between December 2023 and February 2024 was completed |
|
Tung Chung Bay and Tai Ho Wan Baseline Monitoring |
The results of baseline soft shore ecological monitoring at Tung Chung Bay and Tai Ho Wan were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Tung Chung Bay and Tai Ho Wan Impact Monitoring |
Completed |
|
Tung Chung Bay and Tai Ho Wan Post-construction Monitoring |
On-going for TCE, monitoring conducted quarterly |
|
Landscape and Visual |
|
|
Baseline Monitoring |
The results of baseline landscape and visual monitoring were reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4 |
|
Impact Monitoring |
On-going |
|
Site Environmental Audit |
|
|
Regular Site Inspection |
On-going |
|
Dolphin Watching Plan implementation measures |
Completed |
|
Works Vessel Travel Route Plan implementation measures |
Completed |
|
Silt Curtain Deployment Plan implementation measures |
All silt curtain was removed in accordance with the Silt Curtain Deployment Plan and after obtaining the acceptance from EPD |
|
Spill Response Plan implementation measures |
Completed |
|
Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Detailed Compensatory Woodland Planting Plan implementation measures |
Under implementation by the Contractor of Contract 2 |
|
Waste Management Plan implementation measures |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Complaint Hotline and Email Channel |
Under implementation by the Contractor of Contract 1, 2, 3 and 7 |
|
Environmental Log Book |
On-going |
|
Taking into account the construction
works, impact monitoring of air quality, noise and waste management were
carried out in the reporting period. The monitoring schedule of air
quality and noise are provided in Annex E2 and Annex F2 respectively.
The EM&A programme
also involved environmental site inspections and related auditing conducted by
the ET for checking the implementation of the required environmental mitigation
measures recommended in the approved EIA Report and relevant EP submissions,
including Complaint Management Plan, Eco-shoreline Implementation Plan,
Detailed Preservation and/or Translocation Plan for Plant Species of
Conservation Importance, Detailed Compensatory Woodland Planting Plan and Waste
Management Plan.
To promote the environmental
awareness and enhance the environmental performance of the contractors,
environmental trainings and regular environmental management meetings were
conducted during the reporting period, which are summarized as below:
• Four (4) environmental management committee meetings were held among the relevant contractors, ER, ET, IEC and CEDD on 21 and 12 March 2024 (for Contracts 1 and 7) and 20 March 2024 (for Contracts 2 and 3);
•
Environmental toolbox trainings on mosquito control, nuisance to
residence (light pollution/sudden noise/ dusty work), site hygiene (rubbish,
mosquito, rodent control), noise control, wastewater handling, discharge and
treatment facilities, waste management and disposal, chemical handling, dust
control on 1, 6, 8, 13, 15, 20, 22 and 27 March 2024 were conducted for
Contract 1;
•
Environmental toolbox trainings on waste collection, handling and
disposal, protection and preservation of trees on 7 and 18 March 2024 were
conducted for Contract 2;
•
Environmental toolbox trainings on percussive piling, bored piling, mini
piling, steel works, concreting, grouting, chemical waste and handling of
chemical spillage, anti-mosquitos control measures on 5, 7, 12, 14, 19, 21, 26
and 28 March 2024 were conducted for Contract 3;
•
Environmental toolbox trainings on scaffolding, rock bolts, rock dowels,
soil nailing, shotcreting, percussive piling on 6,
13, 20 and 27 March 2024 were conducted for Contract 7.
The status of statutory
environmental compliance with the EP conditions under the EIAO, submission
status under the EP and implementation status of mitigation measures are
presented in Annex C.
The environmental licenses and
permits, including environmental permit, discharge license under Water
Pollution Control Ordinance, registration as chemical waste producer,
construction noise permit and specified processes license, which were valid in
the reporting period are presented in Annex D. No non-compliance with environmental
statutory requirements was recorded.
According to the Updated
EM&A Manual of the Project, impact air quality monitoring in terms of
1-hour Total Suspended Particulate (TSP) was conducted three (3) times every
six (6) days when the highest dust impact was expected. The Action and Limit
Levels of the air quality monitoring is provided in Table 2.1 below.
Table 2.1
Action and Limit Levels for 1-hour TSP
Location |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Monitoring station for Tung Chung East |
279 |
500 |
Portable direct reading dust meters were used to measure
1-hour TSP levels in undertaking the air quality monitoring for the
Project. The proposed use of portable direct reading dust meters was
submitted to IEC and obtained agreement from the IEC as stated in Section 5.5
of the Updated EM&A Manual. With the use of direct reading dust
meter, it can allow prompt and direct results for the EM&A reporting and
the implementation of the event and action plan. The portable direct reading
dust meter would be calibrated every year against High Volume Sampler (HVS) to
check the validity and accuracy of the results measured by direct reading
method.
The monitoring location and
equipment used in the impact air quality monitoring programme
are summarized in Table 2.2 and illustrated in Figure 2.1. Copies of
the calibration certificates for the equipment are presented in Annex E1, which showed that
the portable direct reading dust meter is capable of providing comparable
results with that provided by a HVS.
Table 2.2
Air Quality Monitoring Details
Monitoring Station |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
DM-1 |
Tung Chung Area 56 – Ying Tung Estate |
1-hour TSP |
Three times per six days during the construction period of the Project |
2, 8, 14, 20, 26 and 28 March 2024 |
1-hour TSP Dust Meter SIBATA LD-3B (S/N: 627784) |
Note: It should be noted that impact
monitoring at other construction dust monitoring locations at TCE as stated in
the Updated EM&A Manual will commence after the flat intake (for Monitoring
Stations DM-2, DM-3 and DM-4).
The schedule for air quality
monitoring during the reporting period is provided in Annex E2.
The monitoring results for
1-hour TSP are summarized in Table 2.3. The monitoring data and
the graphical presentation are provided in Annex E3.
Table 2.3
Summary of 1-hour TSP Monitoring Results in the Reporting Period
Monitoring Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
DM-1 |
62 |
42-74 |
279 |
500 |
Major dust sources in the reporting period included haul road
traffic and excavation under the Project.
No
exceedance of Action and Limit Levels was recorded for construction air quality
monitoring in the reporting period. No action was thus required to be
undertaken in accordance with the Event and Action Plan presented in Annex E4.
According to the Updated
EM&A Manual of the Project, impact noise monitoring was conducted once per
week during the construction phase of the Project. The Action and Limit
Level for construction noise of the Project is provided in Table 2.4
below.
Table 2.4
Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A) a, b |
Note:
a Limit level is
exceeded when Leq ≥ 75 dB(A). If works
are to be carried out during restricted hours, the conditions stipulated in the
construction noise permit issued by the Noise Control Authority have to be followed.
b
Reduce to 70 dB
(A) for schools and 65 dB (A) during school examination periods.
Noise monitoring was performed using sound level meter
at the designated monitoring stations NMS-CA-1A ([3]) ([4])
and NMS-CA-4 (Figure 2.2;
Table 2.5) in accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator
was deployed to check the sound level meters at a known sound pressure
level. Details of the deployed equipment are provided in Table 2.5.
Copies of the calibration certificates for the equipment are presented in Annex F1.
Table 2.5 Noise
Monitoring Details
Monitoring Station a |
Location |
Parameter |
Frequency and Duration |
Monitoring Dates |
Equipment |
NMS-CA-1A b |
Residential premise in Tung Chung East – Century Link/Ying Hong Road c |
30-minute measurement between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded. |
Once per week for 30 mins during the construction period of the Project |
2, 8, 14, 20, 26 and 28 March 2024 |
Sound Level Meter: Rion NL-52 (S/N: 00331806)
Acoustic Calibrator: LARSON DAVIS CAL200 (S/N: 16172) |
NMS-CA-4 |
Residential premise in the reclamation area next to Tung Chung East – Ying Tung Estate |
Note:
a It should be noted that
impact monitoring at other construction noise monitoring locations at TCE as
stated in the Updated EM&A Manual will commence after the flat intake of
residential premise in TCE (for Monitoring Station NMS-CA-1) and operation of
schools (for Monitoring Stations NMS-CA-2 and NMS-CA-3).
b Impact monitoring at
monitoring station NMS-CA-1A commenced on 19 September 2018 in view of the
close vicinity of the construction works near the residential area at Century
Link.
c Due to land
handover issue, NMS-CA-1A was relocated to Ying Hong Road which is located 60m
away from the original location. Proposal on the relocation of NMS-CA-1A
was approved by IEC on 23 November 2018. Noise monitoring at the
relocated location commenced since 24 November 2018.
The schedule for noise
monitoring during the reporting period is provided in Annex F2.
Results for noise monitoring are
summarized in Table 2.6. The monitoring data and the graphical
presentation are provided in Annex
F3.
Table 2.6
Summary of Construction Noise Monitoring Results in the Reporting Period
Monitoring Station |
Average, dB(A), |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq (30mins) |
NMS-CA-1A |
67.3 |
66.0-70.2 |
75 |
NMS-CA-4 |
67.9 |
67.0-69.1 |
75 |
Major noise sources during the noise monitoring included noise
from plant operation, craning, piling, haul road traffic, nearby traffic and aircraft as well as nearby construction
sites.
No Limit Level exceedance
was recorded for construction noise monitoring in the reporting period.
However, one (1) Action Level was triggered from one (1) environmental
complaint related to noise nuisance in the reporting period. Investigation
was conducted for the complaint in accordance with the Event and Action Plan (Annex F4) and the details
are provided in Section 2.13.
No monitoring event for impact water
quality monitoring was conducted at all designated monitoring stations
during the reporting period. Water quality monitoring has been suspended
since 3 October 2023 as all reclamation works and marine construction
activities have been completed.
Compensation woodland planting under Contract 2 was
completed on 30 September 2022. With the approval from EPD on the
monitoring proposal in August 2023, the monitoring for compensation woodland
was commenced in September 2023. Quarterly post-planting monitoring for
the compensation woodland was carried out on 12, 18, 23 and 27 March
2024. Photographic record of the compensation woodland planting is
provided in Annex G.
Plant species of conservation
importance, including three individuals of Aquilaria sinensis and 33
individuals of Gmelina chinensis, were identified within works areas for
Contract 2 during the survey conducted in August 2021. All individuals of
Aquilaria sinensis and 31 individuals of Gmelina chinensis were recommended being preserved in-situ while
two individuals of Gmelina chinensis (RT-07 and RT-08) were recommended
being transplanted to the receptor site in accordance with the Detailed
Preservation and/or Translocation Plan for Plant Species of Conservation
Importance approved under Condition 2.21 of EP-519/2016.
Initial tree survey was
conducted in September 2021 under Contract No. NL/2020/02 before the
commencement of construction works. According to the initial tree survey
conducted, the in-situ preserved plant species of conservation
importance of which one individual of Aquilaria sinensis and six
individuals of Gmelina chinensis were found missing.
During the monthly monitoring of the in-situ
preserved plant species of conservation importance in November 2023, one
individual of Aquilaria sinensis and one individual of Enkianthus quinqueflorus
were newly observed and recommended being preserved in-situ.
Registration and measurement for two additional trees were conducted on 4
December 2023.
Monthly monitoring of the in-situ preserved plant species of
conservation importance by the Qualified Personnel (QP) appointed under
Contract 2 was implemented in the reporting period. Health condition was
considered fair for the majority of the in-situ
preserved plant species of conservation importance, of which two individuals of
Gmelina chinensis could not be monitored as a result of unsafe access to
the locations, as recorded during the monitoring carried out on 26 March
2024.
Tree protection zones for the in-situ
preserved plant species of conservation importance were demarcated. No
injuries and/or damages to the individuals of the in-situ preserved
plant species of conservation importance were reported by the QP since the
previous monitoring events. Photographic record and tree schedule of the
preserved plant species of conservation importance monitoring are provided in Annex H1.
The ET will continue to monitor
the implementation of monitoring of in-situ preserved plant species of
conservation importance.
Site visit to the receptor site
for the transplanted plant species of conservation importance under Contract 2
was carried out on 20 January 2022 prior to the commencement of transplantation
works for the transplanted plant species of conservation importance on 21
January 2022.
The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. Replacement planting of new trees of the same species, or other species to the satisfaction of the Project Manager, at the Contractors’ expense would be deemed necessary in accordance with the conditions under the approved Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance. Replacement planting of three (3) Aquilaria sinensis were completed on 28 April 2023. One (1) individual was certified dead by the QP as no living signs were observed on 26 July 2023. The removal of the dead tree and replanting of one (1) individual of Aquilaria sinensis were completed on 19 September 2023.
Monitoring of the replacement
planting of Aquilaria sinensis was carried out on 21 March 2024.
Three (3) individuals of the replacement planting trees were in fair health
condition. Photographic record and tree schedule of Aquilaria sinensis
monitoring are provided in Annex
H2.
The transplanted plant species
of conservation importance were watered twice a week to keep the soil moist
except in days with heavy rainfall. The ET will continue to monitor the
implementation of monitoring of in-situ preserved/ transplanted plant species
of conservation importance.
The construction of vertical eco-shoreline,
mangrove eco-shoreline and rocky eco-shoreline has been substantially
completed. Photographic record is provided in Annex I.
No monitoring of different types of
eco-shorelines was conducted in the reporting period. Monitoring is
conducted for at least 3 years after the completion of eco-shoreline, twice in
wet season and twice in dry season, while ichthyoplankton and juvenile fish
monitoring will be conducted on a monthly basis
covering May to August for at least 3 years, in order to determine the
effectiveness of the eco-shoreline in accordance with the Updated EM&A
Manual and Eco-shoreline Implementation Plan.
No avifauna, epifauna, infauna, vegetation, mudflat
properties, mudflat level and water quality monitoring were conducted in the
reporting period, using point count, transect, fixed point sample, core sample,
fixed gauge at seaward and landward side of the mangrove area, and spot
sample. For details of monitoring methodologies, please refer to the
Eco-shoreline Implementation Plan.
Post-construction soft shore ecological monitoring was
conducted at three (3) monitoring locations at Tung Chung Bay (TCB), situated
in the eastern side (TCB1), southern side (TCB2) and western side (TCB3) as
well as one (1) monitoring location at Tai Ho Wan (THW) as shown in Figure 2.3 during the
reporting period. Representative photographs taken during the impact
monitoring are presented in Figure
2.4.
For qualitative walk-through
surveys, horseshoe crabs and intertidal soft shore communities were recorded
during the post-construction monitoring. The survey results for each
monitoring location are summarized in Table 2.7 below and detailed in Annex J2.
Table 2.7
Summary of Qualitative Walk-through Surveys
Location |
Date and Time a |
Horseshoe Crabs |
Seagrass |
No. of Other Intertidal Species |
||
No. of Species |
No. of Individuals |
No. of Species |
Area Coverage (m2) |
|||
TCB3 |
12/03/2024 13:30-17:30 |
1 |
11 |
1 |
100.1 |
36 |
TCB1 |
26/03/2024 13:00-17:00 |
1 |
1 |
- |
- |
38 |
TCB2 |
26/03/2024 13:00-17:00 |
1 |
11 |
1 |
5.0 |
32 |
THW |
27/03/2024 13:30-17:30 |
1 |
2 |
- |
- |
34 |
Note:
a Quantitative and
qualitative transect surveys were conducted on 12 March 2024 at TCB3, 26 March
2024 at TCB1 and TCB2, and 27 March 2024 at THW.
For the quantitative transect
surveys, a total of 5,916 individuals were recorded from all transects at
monitoring stations TCB1, TCB2, TCB3 and THW. The most abundant group of
intertidal soft shore communities recorded was gastropods, with a total of
5,745 individuals (relative abundance of 97.1% and density of 383.0 individual
m-2). The summary of the top three dominant species at each
shore height of each monitoring station and the complete list of species and
density recorded are presented in Annex J2. When compared with the results obtained
during the baseline monitoring as presented in the Baseline Monitoring Report [5], there was no indication of a change in
the composition of intertidal communities recorded during the reporting period.
The mudflat surface levels at
the four selected monitoring stations in March 2024 and the corresponding XYZ
HK1980 GRID coordinates are presented in Table 2.8. When compared
with the results obtained during the baseline monitoring as presented in the
Baseline Monitoring Report, slight changes with <0.03 mPD
of sediment levels are recorded for the monitoring stations. The ET will
continue to observe the trend of change in sediment levels over time for
further comparison and review.
Table 2.8
Results of Sedimentation Rate Monitoring
Monitoring Station |
Northing (m) |
Easting (m) |
Z level at March 2024 (mPD) |
Remarks |
TCB1 |
816068.724 |
811129.241 |
1.267 |
Soft mudflat |
TCB2 |
815812.756 |
810917.375 |
1.127 |
Soft mudflat |
TCB3 |
816027.441 |
810696.219 |
1.064 |
Soft mudflat |
THW |
817472.049 |
815851.033 |
0.999 |
Soft mudflat |
Based on the post-construction
monitoring results, there was no evidence showing any significant difference in
intertidal communities when compared against the data obtained during baseline
monitoring. No action is thus required to be undertaken in accordance
with the Event and Action Plan presented in Annex J3. The ET will continue to observe the
change in density or the distribution pattern of horseshoe crab, seagrass and
intertidal soft shore communities taking into account
natural fluctuation in respect of the occurrence and distribution pattern.
Site inspections were carried
out on a weekly basis with the Contractor and ER to monitor the implementation
of proper environmental pollution control and mitigation measures for air
quality, noise, water quality, waste management, marine ecology, landscape and
visual impacts and preservation and/or transplantation of plant species of
conservation importance under the Project. In the reporting period, four
(4) site inspections were carried out on 7, 14, 21 and 27 March 2024 for
Contract 1, four (4) site inspections were carried out on 6, 13, 20 and 27
March 2024 for Contract 2, five (5) site inspections were carried out on 1, 8,
15, 20 and 28 March 2024 for Contract 3 and four (4) site inspections were
carried out on 5, 12 19, and 26 March 2024 for Contract 7.
Key observations during the site
inspections are summarized in Table 2.9.
Table 2.9
Key Observations Identified during the Site Inspection in this Reporting
Month
Contract No. |
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
Contract 1 |
7, 14, 21, 27 March 2024 |
Interim Open Rectangular Channel (IORC) • No deficiency was observed. |
• Nil. |
Contract 2 |
6 March 2024 |
Portion 3 • Pipe leakage was observed.
• Sand and debris were observed on haul road.
Portion 6 • Chemical containers were observed placing on the ground. |
Portion 3 • The Contractor was urged to repair the pipe and rectify the situation immediately.
• The Contractor was reminded to clean the sand and debris and keep the haul road clean.
Portion 6 • Contractor was reminded to provide a drip tray for chemicals. |
13 March 2024 |
Portion 3 • Soil exposure on slopes was observed. |
Portion 3 • The Contractor was reminded to provide mitigation measures to prevent potential muddy runoff from slopes, such as covering the slope. |
|
20 March 2024 |
Portion 3 • General waste was observed on ground and slope.
• Proper record was not observed on the wastewater treatment system tank checklist.
TTA • Mud and sand were observed near road gully. served. |
Portion 3 • The Contractor was reminded to remove waste and maintain a good housekeeping.
• The Contractor was reminded to provide proper checking and record on the wastewater treatment system tank checklist.
TTA • The Contractor was urged to remove the mud and sand and prevent them from entering the gullies. |
|
27 March 2024 |
Portion 5 • Accumulated waste was observed. |
Portion 5 • The Contractor was reminded to remove waste in a timely manner. |
|
|
1 March 2024 |
Portion 7, 16a, 16b, 104, TTA • No deficiency was observed |
• Nil. |
8 March 2024 |
Portion 7, 16a, 16b, 104, TTA • No deficiency was observed |
• Nil. |
|
15 March 2024 |
Portion 10 • Chemical container was observed placing on the ground. |
Portion 10 • The Contractor was reminded to provide drip tray for chemicals to avoid spillage. |
|
20 March 2024 |
Portion 104 • Improper Non- Road Mobile Machinery (NRMM) labels were observed on generator.
Portion 10 and 104 • Chemical containers were observed placing on the ground. |
Portion 104 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control Non-road Mobile Machinery) (Emission) Regulation.
Portion 10 and 104 • The Contractor was reminded to provide drip tray for chemicals to avoid spillage. |
|
28 March 2024 |
TTA • General refuse was observed within the tree protection zone.
Portion 10 • Chemical container was observed placing on the ground. |
TTA • The Contractor was reminded to remove waste in a timely manner.
Portion 10 • The Contractor was reminded to provide drip tray for chemicals to avoid spillage. |
|
Contract 7 |
5 March 2024 |
Portion 32 • Appropriate Non- Road Mobile Machinery (NRMM) label was not observed on generator. |
Portion 32 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non- Road Mobile Machinery) (Emission) Regulation. |
12 March 2024 |
Portion 30 • Stagnant water in drip tray was observed. |
Portion 30 • The Contractor was reminded to remove the stagnant water in drip tray to prevent chemical spillage. |
|
19 March 2024 |
Portion 33 • Appropriate Non- Road Mobile Machinery (NRMM) label was not observed on excavator. |
Portion 33 • The Contractor was reminded to affix appropriate NRMM labels in accordance with the Air Pollution Control (Non- Road Mobile Machinery) (Emission) Regulation. |
|
26 March 2024 |
Area E • No deficiency was observed. |
• Nil. |
The Contractors have rectified all of the observations identified during environmental site
inspections in the reporting period. The
Contractors were reminded to implement all relevant mitigation measures
related to construction dust, construction noise, water quality and waste
management outlined in the EIA Report and Updated EM&A Manual.
The Contractors of Contract 1, 2, 3 and 7 have registered as
chemical waste producer. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
All dump trucks engaged on site was equipped with RTTM
system during the reporting period. The Surveillance Team of the ET
conducted regular site inspection on the dump trucks and their track
records. No illegal dumping and landfilling of C&D materials was
found during the reporting period.
Wastes generated during this reporting period include
mainly non-inert construction wastes. Reference has been made to the
waste flow tables prepared by the Contractors. The quantities of
different types of wastes and imported fill materials are summarised
in Table 2.10.
Table 2.10 Quantities of
Different Waste Generated and Imported Fill Materials
Contract No. |
Month/ Year |
Inert C&D Materials a (m3) |
Imported Fill b (sand) (m3) |
Imported Fill c (public fill) (m3) |
Inert Construction Waste Re-used d (m3) |
Non-inert Construction Waste e (m3) |
Recyclable Materials f (kg) |
Chemical Wastes (kg) |
TCNTE (East) |
1 to 31 Jan 24 |
0.0 |
0.0 |
0.0 |
3,452.7 |
322.4 |
0.0 |
1,200.0 |
1 to 29 Feb 24 |
0.0 |
0.0 |
0.0 |
0.0 |
298.7 |
0.0 |
4,000.0 |
|
1 to 31 Mar 24 |
0.0 |
0.0 |
0.0 |
0.0 |
298.0 |
0.0 |
0.0 |
Note:
a Inert construction wastes
include hard rock and large broken concrete, and materials disposed as public
fill.
b
Imported materials
include of sand fill from any source outside of TCNTE.
c Imported sorted public fill
include all G200, G400 and glass gullet (local recycling materials) from any
source outside of TCNTE.
d Reuse of inert construction
waste generated under the TCNTE contracts.
e Non-inert
construction wastes include general refuse disposed at landfill.
f Recyclable materials
include metals, paper, cardboard, plastics and others.
Implementation of applicable landscape and visual mitigation
measures was monitored in accordance with the Updated EM&A Manual.
All measures undertaken by the Contractor during the construction phase and
establishment work phase shall be audited by ET to ensure compliance with the
intended aims of the measures.
The implementation status of the environmental protection
measures is summarized below in Table 2.11. Examples of landscape
and visual mitigation measures are presented in Annex K1. The
monitoring programme for detailed design,
construction and establishment stages is presented in Table 2.12.
Event and Action Plan for Landscape and Visual impacts is stated in Annex K2.
Table 2.11
Implementation Status of Landscape and Visual Mitigation Measures
Landscape and Visual Mitigation Measures during Construction |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
MM1 – Optimization of Construction Areas & Providing Temporary Landscape on Temporary Construction |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA
|
MM2 – Minimize Topographical Changes |
Implementation of the measures were carried out during the detailed design stage of the Project. |
NA |
MM3 – Preservation of Potentially Registerable OVTs, Rare and Protective Vegetation |
Tree Protection Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The Contractors’ performance on the implementation of the tree maintenance and protection measures were observed and checked by the ET weekly during construction period. |
All works contracts |
MM4 – Transplanting of Existing Trees
|
Tree Transplanting Specifications were provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees would unavoidably be affected by the construction works. The Contractors submitted Detailed Preservation and/or Translocation Plan for Plant Species of Conservation Importance under EP condition 2.21. The transplanted plant species of conservation importance were both certified as dead trees by the QP on 15 June 2022 as no living signs were observed. |
Contract 2 |
MM5 – Screen Hoarding
|
All works contracts |
|
MM6 – Adopting Non-dredge Method for the Reclamation |
Not applicable during the reporting period. |
NA |
MM9 – Providing Natural Rock Material/ Planting for Artificial Seawall |
Rock armour reused and construction of eco-shoreline (mangrove eco-shoreline, rocky eco-shoreline and vertical eco-shoreline) in progress. The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 1 |
MM10 – Compensatory Planting |
Not applicable during the reporting period. |
NA |
MM11 – Woodland Restoration |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
Contract 2 |
MM12 – Screen Planting |
Not applicable during the reporting period. |
NA |
MM13 – Roadside Planting |
Not applicable during the reporting period. |
NA |
MM14 – Aesthetic Design of Built Development |
Not applicable during the reporting period. |
NA |
MM15 – Maximise Greening on Structures |
Not applicable during the reporting period. |
NA |
MM16 – Noise Barrier Design |
Not applicable during the reporting period. |
NA |
MM18 – Landscaping on Slopes |
Not applicable during the reporting period. |
NA |
MM20 – Lighting Control |
The implementation of mitigation measures was checked by ET during weekly site inspection. Implementation of the measures by Contractors was observed. |
All works contracts |
Table 2.12
Monitoring Programme for Landscape and Visual
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations of the landscape and visual impact assessments within the EIA should be undertaken by the Engineer and Landscape Architect, to ensure that they fulfil the intentions of the mitigation measures. Any changes to the design, including design changes on site should also be checked |
Report by CEDD / ER confirming that the design conforms to requirements of EP. |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations during the construction period. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the 24-months Establishment Period after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter-signature of report by IEC |
Bi-monthly |
A summary of the Environmental
Mitigation Implementation Schedule is presented in Annex B. The necessary
mitigation measures were implemented properly for the Project.
There was no notification of
summons or prosecution recorded in the reporting period.
Two (2) environmental complaints
related to Contract 3. Investigations were conducted for the
environmental complaints in accordance with the complaint handling process as
stated in the Complaint Management Plan. Environmental complaints in the
reporting period are summarized below.
|
Complaint(s) |
Investigation/Follow up action(s) |
1
|
Environmental complaint related to Contract 3 regarding noise at around 06:00 near the Visionary on 27 February 2024 was referred by EPD on 12 March 2024. |
Based on the information provided by the Contractor with confirmation by RSS, no construction works including preparation work was conducted before 7am from 20 to 27 February. The noise mentioned was likely caused by other construction sites. Nevertheless, the Contractor would provide briefing to workers and frontline staffs regarding noise control. |
2 |
Environmental complaint related to Contract 3 regarding noise near Mun Tung Road and Hei Tung Road on 2 March 2024 was referred by EPD on 12 March 2024. |
Based on the information provided by the Contractor with confirmation by RSS, roadwork was conducted. Percussive breaker was used and the breaker tip was wrapped with sound insulating materials to reduce noise nuisance. In addition, the breaker was removed from the construction site since 6 March. Nevertheless, the Contractor would provide morning brief to workers and frontline staffs regarding noise control. |
Statistics on complaints, notifications of summons, successful
prosecutions are summarised in Annex L.
Works to be undertaken in the next monitoring period of
April 2024 are summarized in Table 3.1 below, together with the key
issues and the key mitigation measures:
Table 3.1
Major Activities for the Next Reporting Period
Activities |
Key Issues |
Key Mitigation Measures |
Contract No. NL/2017/03 - Tung Chung New Town Extension – Reclamation and Advance Works (Contract 1) |
||
Land-based Works |
||
· Box culvert construction · Installation of navigation light at VS2 · Installation of security gate and fence at Seawater Intake |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Potential surface runoff · Noise from plant operation during normal working hours or restricted hours · Dust emission during storage and transfer of sand/ sorted public fill |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Strictly follow requirement under CNP for the use of PMEs and works within restricted period · Use of acoustic mat and other noise mitigation measures when necessary · Regular maintenance of engines and mechanical equipment |
Contract No. NL/2020/02 - Tung Chung New Town Extension – Salt Water Supply System (Contract 2) |
||
Land-based Works |
||
· E&M and ABWF for pumping station at Portion 6 · Construction of service reservoir at Portion 3 · CLP cable duct laying works at Wong Lung Hang at Portion 3 · Watermain laying works at Portion 3 along Chung Yan Road, Man Tung Road, Yu Tung Road Planter and inside WSD facilities · Grouting works at jacking pit at Portion 3 · Watermain laying works at Yi Tung Road at Portion 4 · Manhole construction and pipe laying for drainage works at Portion 5A |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
Contract No. NL/2020/03 - Tung Chung New Town Extension – Major Infrastructure Works in Tung Chung East (Contract 3) |
||
Land-based Works |
||
· Excavation and ELS works at Portion 104 · Excavation and ELS works at CUT no.1, 2, 3, 4 and supporting building · Construction works for CUT no. 1 structure · Back-filling works for CUT 2 · Construction works and furniture installation of PM office at WA9 · Construction works of Contractor office at WA6 · Drainage, Sewerage and watermain works at Road L4, L3, L5, L8, L9 and Portion 16 · DCS works at Road L4 and L3. · Pipe laying works for twin rising mains/ watermain laying at Man Tung Road · Preparation and pipe jacking works at Ying Tung Road · Pipe jacking works at Yi Tung Road · Foundation and backfilling works for noise barrier at Portion 11 · Road and drainage works in Road P1 · Road widening works at Ying Hei Road · Road D4, Road L7, ELS installation
|
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management |
Contract No. NL/2020/07 - Tung Chung New Town Extension – Tai Ho Interchange (Contract 7) |
||
Land-based Works |
||
· Open cut excavation and pipe laying for rising main and watermain at Portion 146-1 to 146-14 · RC for Pak Mong bridge pile cap at Portion 146-3 · Trench excavation, pipe piles and pipe laying works at Portions 32 (Sham Shui Kok Drive), Portion 34 Phase 2, and Portion 38 · Trench excavation and pipe laying works at Portion 32 (Access Road adjacent to MTRC Siu Ho Wan Depot), pipe piles at West Gate · Pipe laying and backfilling at Portion 33 · Establishment of pipe jacking works at Portion 33 · ELS and grout curtain at Portion 32 for Receiving pit · RC construction of retaining walls FR1 · RC works for Pak Mong Subway Extension Phase 1 · ELS at Casting Yard A1 and A2 · Bored piles at A1a and A2b · ELS at A2a and RW-R6 · RC works for RW-R2, RW-R3 and ELS for RW-R4 at Portion 146-2 to 146-4 · RC construction at RW-R7 · Mini-piles at Wall E · GI works for open space at Portions 147-1 &2 · Bored piles at Bridge C Portion 146-12 · Site clearance and tidiness |
· Dust emission · Handling and storage of C&D materials generated from construction activities · Noise from plant operation · Emission of dark smoke from PMEs · Efficiency of wastewater and drainage management · Tree protection |
· Good site practices · Regular water spraying on stockpiles, unpaved haul road and land filling area · Provide tarpaulin sheets coverage on stockpiles · Sorting and reuse of C&D materials as far as practicable · Use of QPME and noise barrier/acoustic mat · Regular maintenance of PMEs · Implementation of wastewater and drainage management · Retain and protect all existing trees and vegetation within the study area which are not directly affected by the works |
The ET will keep track on the construction works to confirm
compliance of environmental requirements and the proper implementation of all
necessary mitigation measures. The ET will also recommend to the
Contractors about the environmental toolbox topics on the abovementioned key
issues for the next reporting period.
The tentative schedules for environmental monitoring in
April 2024 are provided in Annex
M.
This EM&A Report presents the
findings of the EM&A activities undertaken for the TCE Project during the
period from 1 to 31 March 2024 in accordance with the Updated EM&A Manual
and the requirements of the Environmental Permit (EP-519/2016).
Air quality (1-hour TSP), noise,
eco-shoreline, compensation woodland, in-situ preserved plant species of
conservation importance, transplanted plant species of conservation importance
and post-construction soft shore ecological monitoring were carried out in the
reporting period.
The monitoring results for air
quality monitoring (1-hour TSP) complied with the Action/ Limit levels in the
reporting period.
No exceedance of Limit Level was
recorded for construction noise monitoring in the reporting period. However, one (1) Action Level was triggered from one (1)
environmental complaint related to noise nuisance in the reporting period.
Water quality monitoring was
suspended in the reporting period.
Mangrove eco-shoreline, rocky
eco-shoreline and vertical eco-shoreline were completed. No monitoring
was conducted during the reporting period.
Post-construction soft shore
ecological monitoring at Tung Chung Bay and Tai Ho Wan was scheduled during the
reporting period.
Post-planting monitoring of the
compensation woodland was carried out in the reporting month.
Monitoring of the in-situ
preserved plant species of conservation importance and monitoring of the
transplanted plant species of conservation importance were carried out in the
reporting period.
Environmental site inspections
were carried out during the reporting period. Recommendations on remedial
actions were given to the Contractors for the deficiencies identified during
the site inspections.
There were no notification of
summons or prosecution recorded in the reporting period. Two (2)
environmental complaints related to Contract 3. Investigations were
conducted for the environmental complaint in accordance with the complaint handling
process as stated in the Complaint Management Plan.
The ET will keep track on the
construction works to confirm compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
([1])
ERM (2018a). Updated Environmental Monitoring and Audit Manual for
Tung Chung New Town Extension. Deposited to EPD under EP-519/2016
([2])
Arup (2015). Environmental Impact Assessment Report for Tung Chung
New Town Extension. Deposited to EPD under Register No. AEIAR-196/2016
([3])
Impact monitoring at monitoring station NMS-CA-1A commenced on 19
September 2018 in view of the close vicinity of the construction works near the
residential area at Century Link.